to send introductions.
Deal Micro-Teaser
153 MWp solar farm in Kosovo with 10 year PPA
153 MWp/133 MW-AC with a forecasted generation of 196 GWh per year.
All major hurdles are cleared including topographical and geotechnical
surveys finished. The ongoing permitting process, the substation and preliminary works (site preparation, etc) are outstanding.
RTB by March 2025.
10 year PPA LOI for the higher of set price starting at 48.00 EUR/MWh or spot market (HUPX)
Preference for debt including merchant loans but equity or both available.
30+5+5 years land lease with a crossing of the 400 kV grid line
LOI for 65% of total project finance
Technology
Solar PV - Utility-scale
Country
Kosovo
Deal Stage
Early Stage
Company experience with Solar PV - Utility-scale
We have done several projects in Kosovo
Deal Is Seeking
Debt, Equity
Capital Required (USD Equiv.)
$17M
- Financial Model available
- This deal is open to being acquired
- This deal is open to speaking with advisors
- Open to Investor choosing EPC
Proposed Funding Structure
Equity- Equity already arranged0%
- Equity yet to be raised0%
- Debt already arranged81%
- Debt yet to be raised19%
Use of Funds
€1M to finish permitting
€ 5 M for Civil
€ 2 M for Substation
€ 10,810,897 for EPC
These are the remaining funds needed.
All other funds for project are raised.
Generation Capacity
153MWp
Annual Electricity Production
195 MWh/pa
PPA Offtake Status
Negotiation
PPA Type
-MWh Sold Under PPA
-PPA Tariff (USD/kWh)
-PPA Length
10 years
PPA Offtaker Party
Electricity trader
Interested? Introduce yourself
- Deal Is Seeking:Debt, Equity
- Introduce yourself to the:Other
to send introductions.
- Submitted By Project Owner
- Open to Pre-Registrations
- Accepting introductions
- Closed
Unlock the full power of PF Nexus
Our platform is helping run hundreds of renewable energy projects.
- Discover, research and shortlist from 3,631+ companies
- Source deal flow from 7,018+ financial professional
- Get notifications for live project and portfolio opportunities