to send introductions.
Deal Micro-Teaser

96 MW / 430 MWh BESS in Central Bulgaria - Shovel Ready

A 96 MW / 430 MWh BESS project in Bulgaria, RTB with all permits and grid connection in place.

  1. Land:
    Freehold owned.
    Site 100m from the national grid substation, with underground cable connection route.

  2. Grid:
    Connection contract signed with national grid operator.
    Connection fee of €4.7m payable by acquiror.

  3. Permitting:
    Building permit issued Feb 2026, now in force. Fire safety, environmental and utility approvals all obtained.

  • Transaction: -
    100% acquisition sought. Asking price $4.2m (exc. €4.7m connection fee).
    Unlevered IRR 14%.
    Target COD Q2 2028.
Technology
Battery Storage
Country

Bulgaria

Deal Stage

RTB

Company experience with Battery Storage
We are developers and looking for an exit as the project is now RTB. We can assist the future owner and help him during construction, connection and having the system fully operational.
Deal Is Seeking

Acquisition

Capital Required (USD Equiv.)

$4.2M

  • Financial Model available
  • This deal is open to being acquired
  • This deal is open to speaking with advisors
  • Open to Investor choosing EPC
Generation Capacity

430MWp

Annual Electricity Production

157000 MWh/pa

PPA Offtake Status

Negotiation

PPA Type
-
MWh Sold Under PPA
-
PPA Tariff (USD/kWh)
-
PPA Length
-
PPA Offtaker Party
-

Interested? Introduce yourself

  • Deal Is Seeking:Acquisition
  • Introduce yourself to the:Owner
  1. Submitted By Project Owner
  2. Early Access
  3. Accepting introductions
  4. Closed

Unlock the full power of PF Nexus

Our platform is helping run hundreds of renewable energy projects.

  • Discover, research and shortlist from 3,631+ companies
  • Source deal flow from 7,018+ financial professional
  • Get notifications for live project and portfolio opportunities