300MW / 600MWh BESS Portfolio in Eastern Romania - Advanced Development

Two co-located BESS projects in Eastern Romania, 300MW / 600MWh
total (2-hr duration), at a single 220kV POC with the national TSO.

1. Land

  • 49-year public domain concession executed across both sites
    (Aug 2023)

2. Grid

  • ATR issued Oct 2025; connection contract being finalised
    (deadline Oct 2026)
  • Connection tariff: €17k/MW (€5.1M total); 5% covered by
    developer. €9M bond due Nov 2026

3. Permits

  • Environmental permit (APM) imminent; building permit due
    Aug/Sep 2026
  • Grandfathered under new ANRE grid reform framework

Transaction

  • 100% share acquisition of two SPVs
  • Offtake under negotiation; no asking price, NBO process preferred
Technology
Battery Storage (Standalone)
Country

Romania

Deal Stage

Early Stage

Company experience with Battery Storage (Standalone)
Advisory firm representing an experienced Romanian renewable energy developer with an established track record in BESS project development.
Deal Is Seeking

Acquisition, Equity

Capital Required (USD Equiv.)

$0

  • Financial Model available
  • This deal is open to being acquired
  • This deal is open to speaking with advisors
  • Open to Investor choosing EPC
Generation Capacity

250MWp

Annual Electricity Production

500 MWh/pa

PPA Offtake Status

Negotiation

PPA Type
-
MWh Sold Under PPA
-
PPA Tariff (USD/kWh)
-
PPA Length

8 years

PPA Offtaker Party
-

Interested? Introduce yourself

  • Deal Is Seeking:Acquisition, Equity
  • Introduce yourself to the:Advisor
  1. Submitted By Project Owner
  2. Early Access
  3. Accepting introductions
  4. Closed

Unlock the full power of PF Nexus

Our platform is helping run hundreds of renewable energy projects.

  • Discover, research and shortlist from 3,631+ companies
  • Source deal flow from 7,018+ financial professional
  • Get notifications for live project and portfolio opportunities